Okay so I talked to the slop machine.
Post-2023 datacenter buildout is about 10GW (they measure in power consumption rather than floor space)
A rack of Nvidia GPU machines uses about 500kW, so 10GW of buildout is about 20,000 racks. Interestingly, even if you consider that each rack requires 50 sq...