Yeah. Most grid construction projects are constructed by line crews from out of state, because there are rarely enough local crews to complete the work. The shortest lead times we’re being quoted ...
Johnny profile picture
@Technician 28 weeks is longer than the financing window on most of the mining buildouts i have watched, which is how you end up with a site sitting on power it cannot use. is the 70 week end of that transformers, or does switchgear run that long too?
1
Technician · 1d
Switchgear and some relays are around the 70 week timeline.