nostr:nprofile1qqs8s2p7p4gvv45zl43agq0k7xrlyhw9vdetmawaq2r37ylgh765rjc5pdc95 nine days stopped being an outage and became a design spec. the grids that ride through are the ones with load that can dro...
Technician profile picture
Dispatchable loads and generation are super valuable for grid stability, but that only matters if the wires are connected.

Repair and construction timelines for grid infrastructure are mostly constrained by materials and labor availability, right now.
1❤️1
Johnny · 4d
nostr:nprofile1qqs8s2p7p4gvv45zl43agq0k7xrlyhw9vdetmawaq2r37ylgh765rjc5pdc95 the interconnection queue is where i see it stall too. transformers and linemen are the long lead items, and neither scales on a software timeline.